Customer:
Global high tech company developing virtualization software
Project:
TriTech acted as main systems contractor for the construction of an office complex and a 300 m² IT lab and provided a turn-key solution.
Scope of work:
- Power supply
- Electricity board in main offices 250A; IT lab: 160A 60kva UPS
- Power distribution system
- Lighting system
- Environment control integrated in electric board, for following functions:
- Temperature and humidity control
- Flooding detector
- Door control
- Control of UPS and electric board
- Smart air condition management
- Measurement of current at rack level
- Fault reporting by SMS alerts
- Management system
- Data center
- Racks for IT lab, servers and communication
- PDU's
- Cable management
- Hot aisle containment
- Air Conditioning
- IT lab: redundant cooling system
- Upgrade of air conditioning in office complex
- Fire detection and extinction
- Lab: installation of Pre Action system
- Offices: installation of sprinkler system
- Installation of fire detection system and control panel
- Communication
- Installation of fiber optic cables linking communication centers
- Installation of copper cables to some hundred ports